$8 billion. One bridge. No plan.

Make them answer

The federal government wants to land a new interprovincial bridge on Aviation Parkway, which is closed to trucks today. Before it commits billions, Public Services and Procurement Canada should publish the traffic model, the truck routes, the transit plan, what Ontario has said, and the cost.

Show your work.

What the federal government says the bridge will do, and what residents are asking it to show before anything is decided. Housing, Infrastructure and Communities Canada (HICC) now leads the project, taking over from Public Services and Procurement Canada (PSPC).

  • The federal government says the bridge will take heavy trucks off King Edward Avenue.

    Which trucks? Does King Edward close to them afterward? Dangerous goods past the Montfort?

  • The federal government says it will ease congestion between Ottawa and Gatineau.

    Show the rush-hour volumes arriving on the 174 and the 417.

  • The federal government says it will strengthen public transit.

    Which routes? Run by whom? Where is the OC Transpo and STO plan?

  • The federal government says it is working with provincial and municipal partners.

    What has Ontario's Ministry of Transportation said about the 417 and the 174?

  • The plan calls for about 2 km of bridge and 9 km of road changes.

    What do the road changes cost, and which government pays?

$8 billion, block by block.

The Eastern Bridge will cost $8 billion.

Transportation is local. Ottawa's elected leaders should decide which of Ottawa's transportation priorities get funded.

What Ottawa problem does the Kettle Island bridge solve?

Which of Ottawa's elected leaders is asking for it?

  • O-Train upload to Ontario
    $4B, Ottawa's saving over the system's life (2026 memorandum)
  • Transit priorities to 2046
    $2.2B, including the Baseline BRT and the Cumberland Transitway in Orléans (2025 plan)
  • Road priorities to 2046
    $1.1B, including the Brian Coburn widening in Orléans (2025 plan)
  • Stage 3 LRT down payment
    $700M of the $8.3B Stage 3 estimate (2025)

Where the traffic lands.

About 11 km from Autoroute 50 to the 417, including about 2 km of bridge.

New bridge over the Ottawa River, about 2 km

  1. Autoroute 50 at Montée PaiementGatineau
  2. Aviation ParkwayNo trucks allowed todayOpen to trucks?Dangerous goods?
  3. Montfort HospitalAmbulance access?
  4. Montreal RoadWhich intersections get rebuilt?
  5. Ogilvie RoadRush-hour volumes?
  6. Highway 417What does Ontario's MTO say?
The NCC River House swim docks on the Ottawa River, with a long highway bridge carrying trucks drawn across the water behind them.
The West Alignment, one of the federal options, as it would look from the NCC River House, about 550 m away. Unofficial rendering by Jeff Lundeen, built from the federal project maps.

Live in the east end?

Commute on the 174, Montreal Road or Ogilvie every day?

Should your commute absorb a bridge Ottawa never asked for?

Make them answer

The Government of Canada has tried this before.

  1. 2013

    The NCC recommends this corridor. Ontario refuses to back it, and the NCC drops its study.

  2. 2016

    A City of Ottawa and Ontario study finds a downtown truck tunnel feasible, at $1.7 to 2 billion.

  3. 2020

    A refreshed federal study of three east-end corridors is kept for PSPC's internal use. Kettle Island later emerges as the preferred choice.

  4. 2025

    The federal government commits to building the bridge by 2034. MP Mona Fortier says the corridor “does not meet Ottawa's needs.”

  5. Aug 2026

    Crews start site testing on Aviation Parkway, before anyone has decided whether a full impact assessment is required.

  6. Sept 2026

    Ottawa city council votes 23 to 2 to ask for more time to consult.

  7. Nov 2026

    The NCC says Housing, Infrastructure and Communities Canada (HICC) now leads the project, including public engagement.

  8. Now

    The Impact Assessment Agency is deciding whether a full impact assessment is required. The federal government still hasn't shown its work.

Make them answer.

Nothing has been decided yet. These five can make the federal government show its work. Call them. Email them. Ask for a reference number, and keep it.

Housing, Infrastructure and Communities Canada (HICC), Eastern Bridge project team

The department now running the bridge.

According to the NCC, HICC now leads the Eastern Bridge, including public engagement. It took over from PSPC, which never published its numbers. Put your questions on the record with the department now in charge.

Email HICC

Email address: easternbridge-pontdelest@infc.gc.ca

Steven MacKinnon, Minister of Transport, MP for Gatineau

Ottawa didn't elect him.

He announced this bridge in 2025 and has championed it since. As Minister of Transport, he can get the traffic model published. Ask him why Ottawa can't see it.

Email Steven MacKinnon

Email address: Steven.MacKinnon@parl.gc.ca

Call 819-561-5555, Steven MacKinnon's Gatineau office (Gatineau office)

I live in [neighbourhood], Ottawa. I'm calling to ask the Minister to make the federal government publish the Eastern Bridge traffic model before going further.

Tobi Nussbaum, CEO, National Capital Commission

Aviation Parkway is his road.

The NCC keeps trucks off Aviation Parkway today. The bridge only works if that changes. Ask the NCC, in writing, whether it will open the parkway to heavy trucks and dangerous goods. Before the NCC, Nussbaum was the city councillor for Rideau-Rockcliffe, in Ottawa's east end. He knows these streets.

Email Tobi Nussbaum

Email address: Tobi.Nussbaum@ncc-ccn.ca

Call 613-239-5000, National Capital Commission client services (weekdays, 9 a.m. to noon and 1 to 4 p.m.)

I live in [neighbourhood]. I want a written answer from the NCC on whether it will open Aviation Parkway to heavy trucks. Can I get a reference number?

Mona Fortier, MP for Ottawa—Vanier—Gloucester

She said no in 2025. Make her say it louder.

In June 2025 she said the Kettle Island corridor “does not meet Ottawa's needs.” The federal government kept going anyway, and crews have been testing on Aviation Parkway since August. Ask her what she's doing about it now: in caucus, in the House, and with the Minister of Transport.

Email Mona Fortier

Email address: mona.fortier@parl.gc.ca

Call 613-998-1860, Mona Fortier's constituency office (constituency office, 233 Montreal Rd)

I live in [neighbourhood]. I'm calling about the Eastern Bridge. I'd like to know what Ms. Fortier is doing now to stop it going ahead without a published traffic model.

Not in Ottawa—Vanier—Gloucester? Find your MP

Lucille Collard, MPP for Ottawa—Vanier

Ontario stopped this corridor once.

In 2013 the NCC dropped this corridor after Ontario refused to back it. The bridge's traffic would still land on the 417, a provincial highway. Ask your MPP to get Queen's Park on the record.

Email Lucille Collard

Email address: lcollard.mpp.co@liberal.ola.org

Call 613-744-4484, Lucille Collard's constituency office (constituency office, 237 Montreal Rd)

I live in [neighbourhood]. I'm calling about the Eastern Bridge at Kettle Island. I'd like Ms. Collard to ask Ontario to say publicly where it stands.

Not in Ottawa—Vanier? Find your MPP

Get a lawn sign

Bilingual signs for east-end lawns. Signs go on private property with the owner's permission.

Who we are

No Plan, No Bridge is a group of Ottawa residents asking the federal government to publish the traffic model, the truck routes, the transit plan, Ontario's review and the cost before any crossing is built.